Measure ES » Measure ES Project Updates

Measure ES Project Updates

 

 

Your Bond Dollars Building a Better Education!

 

By school site, the following is a list of construction projects and facilities upgrades completed in spring 2020 and in progress during summer 2020:

 
(Photos rotate/change automatically)

Center Street School

  • Addition of new shade structures at two locations on campus
  • Site improvements - Accessible walkways and ramps
 
 
 
 
 

Richmond Street School

  • Addition of an entry Security Vestibule at the main entrance
  • Replacement of all windows in the main building
  • Installation of a shade structure by the kindergarten area
  • Installation of ornamental fencing near the kindergarten area
  • Accessibility upgrade to the restrooms
 
 
 
 

El Segundo Middle School

  • New Security Vestibule at entrance with check-in through main office
  • Main Office Remodel – will be joining the administration office and the library buildings to gain more interior space for a teacher workroom and a lounge
  • New decorative security fencing for school perimeter – completed
  • New Gymnasium/Multi-Use Building – Timing: construction targeted to begin Fall 2021
 
 
 
 
 

El Segundo High School

  • Science Building HVAC Installation – completed
  • New decorative security fencing for school perimeter – nearing completion
  • Security Vestibule for the Main Building A entrance
  • Replacement of all windows in Engineering and Fine Arts Building (Building C)
  • Installation of new baseball field fencing
  • Replace basketball hoops system, bleachers, and refinish flooring in the South Gymnasium
  • Installation of new flooring in the North Gymnasium
  • Library Modernization – Timing: construction targeted to begin Summer 2021
 
 
 
 

ESUSD

  • New teacher workstations in every classroom – completed
  • New furnishings at the Eagles’ Nest Preschool and Arena Virtual High School – completed
  • Audio/Visual improvements in every classroom